Reinforced concrete pad and strip foundation systems

An in situ reinforced concrete pad and strip foundation system typically comprises of items such as blinding, reinforcement and concrete.

Uniclass2015 - Ss_20_05_15_70 Reinforced concrete pad and strip foundation systems
Reference Notes
NBS Code

15-05-15/110 In situ reinforced concrete pad and strip foundation system

-
NRM1

1.1.1 Standard foundations (default)

Rules of measurement | Cost benchmarks

-
Download manufacturer object defintion template

Manufacturer Product Data template

Complete this electronic spreadsheet to ensure that your Reinforced concrete pad and strip foundation systems product information meets the requirements of Level 2 BIM. This is important as it will enable your customers to select, specify and use your products within the BIM environment. Once you have completed this template you can host it on your own website or distribute it to your customers. Please note that we do not host completed product data templates within the BIM Toolkit.

2

Requirement

Visual information to provide general principles of the design. Showing arrangement of system with their relationship to internal and external context, and key project criteria to suit a clients brief. General descriptions would be expected to communicate principles of materiality, scope and context. Expect strategic coordination with other professions to show general principles of the design.

Purpose of information

To provide a visual representation of proposals at a Concept stage and support general spatial coordination.

Plan

The above illustration is for Reinforced concrete pilecap and ground beam foundation systems from the NBS section Concrete foundation systems. This is indicative of the LOD requirements for Reinforced concrete pad and strip foundation systems.

3

Requirement

Visual information to provide developed principles of the design to a greater level of detail. Developed coordination between all professions. Visual development showing coordination for general size and primary relationships between different elements of the construction. Can form a brief for a specialist sub-contractor or fabricator to progress with their technical design, fabrication and installation. This would be expected to include critical dimensional coordination, performance requirements and qualities of finish.

Purpose of information

To provide a visual representation of proposals, confirming brief for technical Design stage supporting full spatial coordination.

Plan
Model
2D Detail

The above illustrations are for Reinforced concrete pilecap and ground beam foundation systems from the NBS section Concrete foundation systems. This is indicative of the LOD requirements for Reinforced concrete pad and strip foundation systems.

4

Requirement

Visual information to provide fixed principles of the design supporting procurement. Developed coordination between all professions. Visual representations showing coordination for general size and relationships between different elements of the construction. Graphical representation of system, dimensionally accurate indicating primary performance characteristics. Graphical information represented may alter dependant on visual information to be produced, eg: Scope of work drawings, setting out, floor loading etc Typical / Installation details separately produced linked to model element and adjacent constructions.

Purpose of information

To provide a visual representation of proposals at a Technical Design stage supporting full spatial coordination.

Plan
Model
2D Detail

The above illustrations are for Reinforced concrete pilecap and ground beam foundation systems from the NBS section Concrete foundation systems. This is indicative of the LOD requirements for Reinforced concrete pad and strip foundation systems.

5

Requirement

Visual information to provide full information to support construction / installation. Developed coordination between all professions. Visual representations showing final coordination for size and relationships between different elements of the construction. Graphical representation of system, dimensionally accurate indicating primary performance characteristics and sufficient information to support installation. Typical / Installation details separately produced linked to model element and adjacent constructions.

Purpose of information

To be updated during the construction process to reflect the final design, and to provide a future reference to sit alongside the O&M Manuals.

Plan
Model
2D Detail

The above illustrations are for Reinforced concrete pilecap and ground beam foundation systems from the NBS section Concrete foundation systems. This is indicative of the LOD requirements for Reinforced concrete pad and strip foundation systems.

Download manufacturer object defintion template

Manufacturer Product Data template

Complete this electronic spreadsheet to ensure that your Reinforced concrete pad and strip foundation systems product information meets the requirements of Level 2 BIM. This is important as it will enable your customers to select, specify and use your products within the BIM environment. Once you have completed this template you can host it on your own website or distribute it to your customers. Please note that we do not host completed product data templates within the BIM Toolkit.

2

Provide an outline description of the deliverable.

Name Definition
Description A description of the type of object to detail any design intent.
3

Provide information relevant to the specific performance of the deliverable. Information to specify the completion (cleaning, testing, spares, training...) of the deliverable should also be provided in the associated specification.

Name Definition
Drawings and reinforcement schedules for reinforced concrete construction Building component designations, Reinforcement schedules and Reinforcement drawings.
Geotechnical design Standards, Design category and Ground investigation report.
Loads applied to foundations Design loads.
Reinforcement detailing Detailing rules for particular situations, Order of priority when clashes occur and Reinforcement for crack control.
Settlement criteria for buildings and structures Requirement and Permitted settlement at serviceability limit state.
4

Provide information relevant to the specific child products of the deliverable to allow suitable products from manufacturers to be selected. Information covering the completion and execution of the deliverable and its child products should also be provided.

Name Definition
Blinding Products such as Designated concrete.
Reinforcement - Type of reinforcement Products such as Carbon steel fabric reinforcement.
Reinforcement - Reinforcement accessories Products such as Carbon steel post-installed starter bars.
Concrete Products such as Designated concrete.
Designed joints - Joint type The Designed joints - Joint type of the Reinforced concrete pad and strip foundation systems.
Designed joints - Joint filler Products such as Bitumen-impregnated softboard joint fillers.
Designed joints - Joint accessories Products such as Carbon steel dowel bars.
Cast in accessories Products such as Holding down bolt assemblies.
5

Provide information relevant to the specific child products of the deliverable to allow for purchasing. Information covering the completion and execution of the deliverable and its child products should also be provided.

Name Definition
Blinding Products such as Designated concrete.
Reinforcement - Type of reinforcement Products such as Carbon steel fabric reinforcement.
Reinforcement - Reinforcement accessories Products such as Carbon steel post-installed starter bars.
Concrete Products such as Designated concrete.
Designed joints - Joint type The Designed joints - Joint type of the Reinforced concrete pad and strip foundation systems.
Designed joints - Joint filler Products such as Bitumen-impregnated softboard joint fillers.
Designed joints - Joint accessories Products such as Carbon steel dowel bars.
Cast in accessories Products such as Holding down bolt assemblies.
6

Provide the information specific to the installed deliverable that is required for operation and maintenance. Information covering the detailed maintenance should also be provided in the associated PDF manuals.

Name Definition
Asset type An indication of whether the object is fixed or movable.
Manufacturer Email address for the organisation responsible for supplying or manufacturing the object
ModelNumber The product, item or unit number assigned by the manufacturer of the object.
Warranty guarantor (parts) Email address for the organisation responsible for the parts warranty.
Warranty duration (parts) Duration of parts warranty.
Warranty guarantor (labour) Email address for the organisation responsible for the labour warranty.
Warranty duration (labour) Duration of labour warranty.
Warranty duration unit Duration of warranties (typical value is 'years').
Replacement cost An indicative cost for unit replacement.
Expected life The typical service life of the object.
Duration unit Duration of expected life (typical value is 'years')
Warranty description Description of the warranty content and any exclusions.
Nominal length Typically the larger or primary horizontal dimension.
Nominal width Nominal width of product, typically the characteristic or secondary horizontal or characteristic dimension.
Nominal height Typically the vertical or secondary characteristic dimension.
ModelReference The name of the object as used by the manufacturer.
Shape Characteristic shape of product.
Size Characteristic size of product.
Colour Characteristic or primary colour of product.
Finish Characteristic or primary finish of product.
Grade Standard grading which the product corresponds.
Material Characteristic or primary material of product.
Constituents Optional constituent features, parts or finishes.
Features Other important characteristics or features relevant to product specification.
Accessibility performance The accessibility issue(s) which the object satisfies.
Sustainability performance Description of the sustainability issue(s) which the object satisfies
Code performance The code compliance requirement(s) which the object satisfies
Serial number The serial number assigned to an occurrence of a product by the manufacturer (per instance).
Installation date The date that the manufactured item was installed (per instance).
Warranty start date The date on which the warranty commences.
Tag number The tag number assigned to an occurrence of a product by the occupier (per instance).